Property request · wetlands permit
Lucas S. & Sherri M. Geiger: install 232 linear feet of riprap revetment and install 30 linear feet of riprap sill (Hull Creek)
Wetlands Board decides (county’s record, Nov 10)Approved · Nov 10
A step the records show opens the record itself.
In plain words
Lucas S. & Sherri M. Geiger asked to install 232 linear feet of riprap revetment and 30 linear feet of riprap sill along the shoreline of Hull Creek and 697 Earls Lane.1 The Wetlands Board decides Application No. 25-2105.2 On October 14, 2025, Craig Palubinski, agent for the owner, described the project and said six square feet of needle rush will be impacted.2 After discussion of the possible need for wetland credits, Robert Vanlandingham made a motion to table the application until the November meeting.2 On November 10, 2025, Philip Marston said VARTF credits are available, and George Rew moved to approve the project upon proof of payment to VARTF.3 Robert Vanlandingham seconded the motion and the Board approved.3
Summarized from the county’s records, September 29.
Where each sentence comes from
- “to install 232 linear feet of riprap revetment and install 30 linear feet of riprap sill along the shoreline of Hull Creek and 697 Earls Lane”The matter as the records title it
- “Application No. 25-2105 Lucas S. & Sherri M. Geiger” … “Craig Palubinski, agent for the owner, described the project. He noted that there is six square feet of needle rush that will be impacted.” … “After review of the project and the possible need for wetland credits, Robert Vanlandingham made a motion to table the application until the November meeting.”Oct 14, 2025 · Wetlands Board · In the minutes
- “Philip Marston informed the Board that VARTF credits are available for the Lucas S. & Sherri M. Geiger project” … “George Rew made a motion to approve the project upon proof of payment to VARTF” … “Robert Vanlandingham seconded the motion and the Board approved.”Nov 10, 2025 · Wetlands Board · In the minutes
Written automatically from the county’s records. Each sentence has to quote the record it comes from, word for word, or it’s left out. The records have the final say.
The official wording
Application No. 25-2105 Lucas S. & Sherri M. Geiger – to install 232 linear feet of riprap revetment and install 30 linear feet of riprap sill along the shoreline of Hull Creek and 697 Earls Lane.
Words the law defines
Wetlands board
“‘Wetlands board’ or ‘board’ means a board created pursuant to § 28.2-1303.”
Code of Virginia § 28.2-1300, Chapter 13. Wetlands
What’s happened
- Mon10Nov
Wetlands Board · a vote
ApprovedThe Board’s vote
After review, Robert Vanlandingham made a motion to approve the application. George Rew seconded the motion and the Board approved with Albert Fisher abstaining.
Moved by Vanlandingham, seconded by Rew
- Tue14Oct
Wetlands Board · a vote
TabledThe Board’s vote
After review of the project and the possible need for wetland credits, Robert Vanlandingham made a motion to table the application until the November meeting. George Rew seconded the motion and the Board unanimously approved.
Moved by Vanlandingham, seconded by Rew
Meeting by meeting, newest first, in the records’ own words. Each vote names the minutes it’s written in.
The records
- Mon10Nov
- Tue14Oct
Gathered from Northumberland County’s agendas, minutes and notices. Checked October 26.