Lawrence Liesfeld: install 70 linear feet of riprap revetment (Cockrells Creek)

  1. Wetlands Board hearing (county’s record, Apr 14)Apr 14

  2. Wetlands Board decides (county’s record, Apr 14)Approved, unanimously · Apr 14

A step the records show opens the record itself.

About the Wetlands Board

In plain words

Lawrence Liesfeld has applied to put in 70 linear feet of riprap revetment, a rock barrier, along the shoreline at Cockrells Creek and 103 Mollys Lane.1 The request is Application No. 26-0161, and the Wetlands Board took it up on April 14, 2026.2 Bryan McDearmon, agent for the owner, described the project and noted 2 sections of riprap.2 Albert Fisher said both of those areas were severely undercut, and McDearmon said a living shoreline was not considered due to the trees and boat traffic.2 There were no objections, and Albert Fisher made a motion to approve the project as submitted for three years.2

Summarized from the county’s records, September 26.

Where each sentence comes from
  1. “Lawrence Liesfeld – to install 70 linear feet of riprap revetment along the shoreline of Cockrells Creek and 103 Mollys Lane”The matter as the records title it
  2. “Application No. 26-0161 Lawrence Liesfeld” … “Bryan McDearmon, agent for the owner, described the project noting 2 sections of riprap” … “Albert Fisher noted that both of those areas were severely undercut. Bryan McDearmon said a living shoreline was not considered due to the trees and boat traffic.” … “there being no objections, Albert Fisher made a motion to approve the project as submitted for three years”Apr 14, 2026 · Wetlands Board · In the minutes

Written automatically from the county’s records. Each sentence has to quote the record it comes from, word for word, or it’s left out. The records have the final say.

The official wording

Application No. 26-0161 Lawrence Liesfeld – to install 70 linear feet of riprap revetment along the shoreline of Cockrells Creek and 103 Mollys Lane.

Words the law defines

  • Wetlands board
    “‘Wetlands board’ or ‘board’ means a board created pursuant to § 28.2-1303.”

    Code of Virginia § 28.2-1300, Chapter 13. Wetlands

What’s happened

  1. Tue14Apr

    Wetlands Board · a vote

    ApprovedLawrence Liesfeld: install 70 linear feet of riprap revetment (Cockrells Creek)

    After review of the project and there being no objections, Albert Fisher made a motion to approve the project as submitted for three years. Robert Vanlandingham seconded the motion and the Board unanimously approved.

    Moved by Fisher, seconded by Vanlandingham

    Minutes, Apr 14Open it in the meeting →

Meeting by meeting, newest first, in the records’ own words. Each vote names the minutes it’s written in.

The records

Gathered from Northumberland County’s agendas, minutes and notices. Checked October 26.

Something wrong here?

If you know something on this page is wrong, say so. A person at County Voice reads each one. One that checks out is corrected here, with the date. The county’s and the state’s own records aren’t changed.

Never shown on the site, and not used for anything else.

Disagreeing with a decision isn’t a correction. To be heard on one, see what’s coming up.

How a wetlands permit is decided

Work in tidal wetlands and along the shoreline, such as riprap, bulkheads and sills, needs a permit. The county's Wetlands Board decides these applications after an advertised public hearing.

Applications are also filed with the Virginia Marine Resources Commission, which assigns the application number used to follow a request.

The law: Va. Code § 28.2-1302 (Adoption of wetlands zoning ordinance; terms of ordinance). This describes the general process, not this decision.