Property request · wetlands permit
Robert Muzzio: install 70 linear feet of riprap revetment (Cockrell Creek)
Wetlands Board decides (county’s record, Oct 14)Approved, unanimously · Oct 14
A step the records show opens the record itself.
In plain words
Robert Muzzio asked the Wetlands Board for approval to "install 70 linear feet of riprap revetment along the shoreline of Cockrell Creek and 2692 Fleeton Road" under Application No. 25-1926.1 At the Wetlands Board meeting on October 14, 2025, "Joseph Scott, agent for the owner, described the project."2 With "there being no objections, George Rew made a motion to approve the application as submitted for three years."2 "Robert Vanlandingham seconded the motion and the Board unanimously approved."2 On November 10, 2025, Philip Marston told the Board that Muzzio "had a project (V.M.R.C. 25-1926) approved with wetland impacts" and "had applied to VARTF to compensate for those impacts".3
Summarized from the county’s records, September 30.
Where each sentence comes from
- “Application No. 25-1926 Robert Muzzio – to install 70 linear feet of riprap revetment along the shoreline of Cockrell Creek and 2692 Fleeton Road.”The matter as the records title it
- “Joseph Scott, agent for the owner, described the project.” … “there being no objections, George Rew made a motion to approve the application as submitted for three years” … “Robert Vanlandingham seconded the motion and the Board unanimously approved.”Oct 14, 2025 · Wetlands Board · In the minutes
- “had a project (V.M.R.C. 25-1926) approved with wetland impacts” … “had applied to VARTF to compensate for those impacts”Nov 10, 2025 · Wetlands Board · In the minutes
Written automatically from the county’s records. Each sentence has to quote the record it comes from, word for word, or it’s left out. The records have the final say.
The official wording
Application No. 25-1926 Robert Muzzio – to install 70 linear feet of riprap revetment along the shoreline of Cockrell Creek and 2692 Fleeton Road.
Words the law defines
Wetlands board
“‘Wetlands board’ or ‘board’ means a board created pursuant to § 28.2-1303.”
Code of Virginia § 28.2-1300, Chapter 13. Wetlands
What’s happened
- Mon10Nov
- Tue14Oct
Wetlands Board · a vote
ApprovedRobert Muzzio: install 70 linear feet of riprap revetment (Cockrell Creek)
After review of the project and there being no objections, George Rew made a motion to approve the application as submitted for three years. Robert Vanlandingham seconded the motion and the Board unanimously approved.
Moved by Rew, seconded by Vanlandingham
Meeting by meeting, newest first, in the records’ own words. Each vote names the minutes it’s written in.
The records
- Mon10Nov
- Tue14Oct
Gathered from Northumberland County’s agendas, minutes and notices. Checked October 26.