Fleeton, LLC: install 530 linear feet of riprap revetment (Spences Creek)

  1. Wetlands Board hearing (county’s record, Jan 14)Jan 14

  2. Wetlands Board decides (county’s record, Jan 14)Approved, unanimously · Jan 14

A step the records show opens the record itself.

About the Wetlands Board

In plain words

Fleeton, LLC applied to install 530 linear feet of riprap revetment along the shoreline of Spences Creek and Tax Map Parcel #28-1-115-A on Harbor View Drive.1 Mike Cappell, acting on behalf of Roger McKinley, agent for the owner, described the project and said a living shoreline would not work because the site is North facing and shaded.2 Robert Vanlandingham noted the project did not appear to be adequately staked, and Mike Cappell agreed to do a more complete staking of the site.2 Albert Fisher made a motion to approve the application for three years upon the site being properly staked and inspected.2 Robert Vanlandingham seconded the motion and the Board unanimously approved.2

Summarized from the county’s records, September 30.

Where each sentence comes from
  1. “Application No. 24-2741 Fleeton, LLC – to install 530 linear feet of riprap revetment along the shoreline of Spences Creek and Tax Map Parcel #28-1-115-A on Harbor View Drive.”The matter as the records title it
  2. “Mike Cappell, acting on behalf of Roger McKinley, agent for the owner, described the project. He stated that a living shoreline would not work as it is North facing and is shaded by overhead growth.” … “Robert Vanlandingham noted that the project did not appear to be adequately staked. Mike Cappell agreed to do a more complete staking of the site.” … “Albert Fisher made a motion to approve the application for three years upon the site being properly staked and inspected” … “Robert Vanlandingham seconded the motion and the Board unanimously approved.”Jan 14, 2025 · Wetlands Board · In the minutes

Written automatically from the county’s records. Each sentence has to quote the record it comes from, word for word, or it’s left out. The records have the final say.

The official wording

Application No. 24-2741 Fleeton, LLC – to install 530 linear feet of riprap revetment along the shoreline of Spences Creek and Tax Map Parcel #28-1-115-A on Harbor View Drive.

What’s happened

  1. Tue14Jan

    Wetlands Board · a vote

    ApprovedFleeton, LLC: install 530 linear feet of riprap revetment (Spences Creek)

    After review of the project and there being no objections, Albert Fisher made a motion to approve the application for three years upon the site being properly staked and inspected. Robert… Show all

    Moved by Fisher, seconded by Vanlandingham

    Minutes, Jan 14Open it in the meeting →

Meeting by meeting, newest first, in the records’ own words. Each vote names the minutes it’s written in.

The records

Gathered from Northumberland County’s agendas, minutes and notices. Checked October 26.

Something wrong here?

If you know something on this page is wrong, say so. A person at County Voice reads each one. One that checks out is corrected here, with the date. The county’s and the state’s own records aren’t changed.

Never shown on the site, and not used for anything else.

Disagreeing with a decision isn’t a correction. To be heard on one, see what’s coming up.

How a wetlands permit is decided

Work in tidal wetlands and along the shoreline, such as riprap, bulkheads and sills, needs a permit. The county's Wetlands Board decides these applications after an advertised public hearing.

Applications are also filed with the Virginia Marine Resources Commission, which assigns the application number used to follow a request.

The law: Va. Code § 28.2-1302 (Adoption of wetlands zoning ordinance; terms of ordinance). This describes the general process, not this decision.