Carol Hurst: install 102 linear feet of riprap sill and install 70 linear feet of riprap revetment (Jarvis Creek)

  1. Wetlands Board hearing (county’s record, Jan 13)Jan 13

  2. Wetlands Board decides (county’s record, Jan 13)Approved, unanimously · Jan 13

A step the records show opens the record itself.

About the Wetlands Board

In plain words

Carol Hurst has applied to install 102 linear feet of riprap sill and 70 linear feet of riprap revetment along the shoreline of Jarvis Creek at 257 Landon Hall Lane.1 The Wetlands Board heard Application No. 25-2518 on January 13, 2026.2 Kelsey Haynie, agent for the owner, described the project and said 70 feet of the shoreline is severely eroded.2 She said the pool and house are close and could not be graded, so a riprap revetment is planned for that 70 feet.2 Robert Vanlandingham moved to approve the application as submitted for three years, Albert Fisher seconded, and the Board approved it unanimously.2

Summarized from the county’s records, September 26.

Where each sentence comes from
  1. “to install 102 linear feet of riprap sill and install 70 linear feet of riprap revetment along the shoreline of Jarvis Creek and 257 Landon Hall Lane”The matter as the records title it
  2. “Application No. 25-2518 Carol Hurst” … “Kelsey Haynie, agent for the owner, described the project” … “70 feet is severely eroded” … “the pool and house are really close and they could not grade so they are installing a riprap revetment for that 70 feet” … “Robert Vanlandingham made a motion to approve the application as submitted for three years. Albert Fisher seconded the motion and the Board unanimously approved.”Jan 13, 2026 · Wetlands Board · In the minutes

Written automatically from the county’s records. Each sentence has to quote the record it comes from, word for word, or it’s left out. The records have the final say.

The official wording

Application No. 25-2518 Carol Hurst – to install 102 linear feet of riprap sill and install 70 linear feet of riprap revetment along the shoreline of Jarvis Creek and 257 Landon Hall Lane.

Words the law defines

  • Wetlands board
    “‘Wetlands board’ or ‘board’ means a board created pursuant to § 28.2-1303.”

    Code of Virginia § 28.2-1300, Chapter 13. Wetlands

What’s happened

  1. Tue13Jan

    Wetlands Board · a vote

    ApprovedThe Board’s vote

    After further review of the project, Robert Vanlandingham made a motion to approve the application as submitted for three years. Albert Fisher seconded the motion and the Board unanimously approved.

    Moved by Vanlandingham, seconded by Fisher

    Minutes, Jan 13Open it in the meeting →

Meeting by meeting, newest first, in the records’ own words. Each vote names the minutes it’s written in.

The records

Gathered from Northumberland County’s agendas, minutes and notices. Checked October 26.

Something wrong here?

If you know something on this page is wrong, say so. A person at County Voice reads each one. One that checks out is corrected here, with the date. The county’s and the state’s own records aren’t changed.

Never shown on the site, and not used for anything else.

Disagreeing with a decision isn’t a correction. To be heard on one, see what’s coming up.

How a wetlands permit is decided

Work in tidal wetlands and along the shoreline, such as riprap, bulkheads and sills, needs a permit. The county's Wetlands Board decides these applications after an advertised public hearing.

Applications are also filed with the Virginia Marine Resources Commission, which assigns the application number used to follow a request.

The law: Va. Code § 28.2-1302 (Adoption of wetlands zoning ordinance; terms of ordinance). This describes the general process, not this decision.