Margaret Short: install 130 linear feet of riprap revetment (Indian Creek)

  1. Wetlands Board hearing (county’s record, Mar 10)Mar 10

  2. Wetlands Board decides (county’s record, Mar 10)Approved, unanimously · Mar 10

A step the records show opens the record itself.

About the Wetlands Board

In plain words

Margaret Short has applied to put in 130 linear feet of riprap revetment, a rock barrier, along the shoreline at Indian Creek and 449 Tuckahoe Drive.1 The Wetlands Board heard Application No. 26-0150 on March 10, 2026.2 Joseph Scott, agent, described the project and said a fringe marsh there is not protecting the upland bank, so he didn't think a living shoreline would work.2 Albert Fisher moved to approve the application as submitted for three years, George Rew seconded, and the Board approved it unanimously for three years.2

Summarized from the county’s records, September 26.

Where each sentence comes from
  1. “to install 130 linear feet of riprap revetment along the shoreline of Indian Creek and 449 Tuckahoe Drive”The matter as the records title it
  2. “Application No. 26-0150 Margaret Short” … “Joseph Scott, agent, described the project. He informed the Board that there is a fringe marsh there already that is not protecting the upland bank so he didn’t think a living shoreline would work.” … “Albert Fisher made a motion to approve the application as submitted for three years. George Rew seconded the motion and the Board unanimously approved for three years.”Mar 10, 2026 · Wetlands Board · In the minutes

Written automatically from the county’s records. Each sentence has to quote the record it comes from, word for word, or it’s left out. The records have the final say.

The official wording

Application No. 26-0150 Margaret Short – to install 130 linear feet of riprap revetment along the shoreline of Indian Creek and 449 Tuckahoe Drive.

Words the law defines

  • Wetlands board
    “‘Wetlands board’ or ‘board’ means a board created pursuant to § 28.2-1303.”

    Code of Virginia § 28.2-1300, Chapter 13. Wetlands

What’s happened

  1. Tue10Mar

    Wetlands Board · a vote

    ApprovedMargaret Short: install 130 linear feet of riprap revetment (Indian Creek)

    After further review of the project, Albert Fisher made a motion to approve the application as submitted for three years. George Rew seconded the motion and the Board unanimously approved for three years.

    Moved by Fisher, seconded by Rew

    Minutes, Mar 10Open it in the meeting →

Meeting by meeting, newest first, in the records’ own words. Each vote names the minutes it’s written in.

The records

Gathered from Northumberland County’s agendas, minutes and notices. Checked October 26.

Something wrong here?

If you know something on this page is wrong, say so. A person at County Voice reads each one. One that checks out is corrected here, with the date. The county’s and the state’s own records aren’t changed.

Never shown on the site, and not used for anything else.

Disagreeing with a decision isn’t a correction. To be heard on one, see what’s coming up.

How a wetlands permit is decided

Work in tidal wetlands and along the shoreline, such as riprap, bulkheads and sills, needs a permit. The county's Wetlands Board decides these applications after an advertised public hearing.

Applications are also filed with the Virginia Marine Resources Commission, which assigns the application number used to follow a request.

The law: Va. Code § 28.2-1302 (Adoption of wetlands zoning ordinance; terms of ordinance). This describes the general process, not this decision.