Wetlands Board
Tuesday, June 9, 2026
Minutes postedAgendaMinutes, Jun 9
Decided 3
- SGL 259 LLC and Raj Bansal: install 240 linear feet of armor stone revetment channelward of a failing bulkhead and to remove four failed groins and construct four low-profile timber groins each 48 feet channelward of MHW (Potomac River)
Approved
Moved by Fisher, seconded by Vanlandingham
- Edwin A. Sisson and Cowart Seafood Corporation: conduct a maintenance dredge of berthing areas, adjacent to existing wharves, of 170 cubic yards of spoils material (Penny Creek)
Approved
Moved by Vanlandingham, seconded by Fisher
- Scott B. Johnson: install 170 linear feet of bulkhead channelward of an existing bulkhead (Little Wicomico River)
Tabled
Moved by Rew, seconded by Fisher
In the order of the minutes. Each quote opens the minutes where it’s written. Routine votes (approving the agenda and minutes, entering and leaving closed session, adjourning) aren’t listed.