Property request · wetlands permit
Eileen Tullner: repair 225 linear feet of existing riprap revetment and install 25 linear feet of riprap revetment (Prentice Creek)
Wetlands Board decides (county’s record, Aug 11)Approved, unanimously · Aug 11
A step the records show opens the record itself.
In plain words
Eileen Tullner has applied to the Wetlands Board to repair 225 linear feet of existing riprap revetment and install 25 linear feet of new riprap revetment.1 The work, filed as Application No. 26-1485, is along the shoreline of Prentice Creek and 2054 Ditchley Road.1 At the Wetlands Board meeting on August 11, 2026, Joseph Scott, agent for the owner, described the project.2 He said there is a 26-mile fetch from the SE, and that the 25 feet of riprap revetment would sit behind any wetland vegetation.2 With no objections, Robert Vanlandingham made a motion to approve the application as submitted for three years.2
Summarized from the county’s records, September 26.
Where each sentence comes from
- “Eileen Tullner – to repair 225 linear feet of existing riprap revetment and install 25 linear feet of riprap revetment” … “Application No. 26-1485” … “along the shoreline of Prentice Creek and 2054 Ditchley Road”The matter as the records title it
- “Joseph Scott, agent for the owner, described the project.” … “He noted that there is a 26-mile fetch from the SE. He also noted that the 25 feet of riprap revetment would be behind any wetland vegetation.” … “there being no objections, Robert Vanlandingham made a motion to approve the application as submitted for three years”Aug 11, 2026 · Wetlands Board · In the minutes
Written automatically from the county’s records. Each sentence has to quote the record it comes from, word for word, or it’s left out. The records have the final say.
The official wording
Application No. 26-1485 Eileen Tullner – to repair 225 linear feet of existing riprap revetment and install 25 linear feet of riprap revetment along the shoreline of Prentice Creek and 2054 Ditchley Road.
Words the law defines
Wetlands board
“‘Wetlands board’ or ‘board’ means a board created pursuant to § 28.2-1303.”
Code of Virginia § 28.2-1300, Chapter 13. Wetlands
What’s happened
- Tue11Aug
Wetlands Board · a vote
ApprovedThe Board’s vote
After reviewing the project and there being no objections, Robert Vanlandingham made a motion to approve the application as submitted for three years. George Rew seconded the motion and the Board unanimously approved.
Moved by Vanlandingham, seconded by Rew