Penelope Weinheimer: install 195 linear feet of riprap revetment (Hull Creek)

  1. Wetlands Board hearing (county’s record, Aug 11)Aug 11

  2. Wetlands Board decides (county’s record, Aug 11)Approved, unanimously · Aug 11

A step the records show opens the record itself.

About the Wetlands Board

In plain words

Application No. 26-1463, from Penelope Weinheimer, asks to install 195 linear feet of riprap revetment, a rock bank covering, along the shoreline of Hull Creek and 162 Spinnaker Lane.1 The Wetlands Board took up the application on Aug 11, 2026, where Joseph Scott, agent for the owner, described the project.2,3 He said a living shoreline was not considered because the banks had eroded up to 4 and 5 feet high.2 He said stabilizing the banks would mean removing a lot of trees and grading the banks.2 There were no objections, and Albert Fisher made a motion to approve the application as submitted for three years.2

Summarized from the county’s records, September 26.

Where each sentence comes from
  1. “Application No. 26-1463 Penelope Weinheimer – to install 195 linear feet of riprap revetment along the shoreline of Hull Creek and 162 Spinnaker Lane.”The matter as the records title it
  2. “Joseph Scott, agent for the owner, described the project.” … “He noted that a living shoreline was not considered because the banks had eroded up to 4 and 5 feet high.” … “in order to stabilize it there would be a lot of trees removed and the banks graded” … “After reviewing the project and there being no objections, Albert Fisher made a motion to approve the application as submitted for three years.”Aug 11, 2026 · Wetlands Board · In the minutes
  3. “Application No. 26-1463 Penelope Weinheimer”Aug 11, 2026 · Wetlands Board · On the agenda

Written automatically from the county’s records. Each sentence has to quote the record it comes from, word for word, or it’s left out. The records have the final say.

The official wording

Application No. 26-1463 Penelope Weinheimer – to install 195 linear feet of riprap revetment along the shoreline of Hull Creek and 162 Spinnaker Lane.

Words the law defines

  • Wetlands board
    “‘Wetlands board’ or ‘board’ means a board created pursuant to § 28.2-1303.”

    Code of Virginia § 28.2-1300, Chapter 13. Wetlands

What’s happened

  1. Tue11Aug

    Wetlands Board · a vote

    ApprovedPenelope Weinheimer: install 195 linear feet of riprap revetment (Hull Creek)

    After reviewing the project and there being no objections, Albert Fisher made a motion to approve the application as submitted for three years. George Rew seconded the motion and the Board unanimously approved.

    Moved by Fisher, seconded by Rew

    Minutes, Aug 11Open it in the meeting →

Meeting by meeting, newest first, in the records’ own words. Each vote names the minutes it’s written in.

The records

Gathered from Northumberland County’s agendas, minutes and notices. Checked October 26.

Something wrong here?

If you know something on this page is wrong, say so. A person at County Voice reads each one. One that checks out is corrected here, with the date. The county’s and the state’s own records aren’t changed.

Never shown on the site, and not used for anything else.

Disagreeing with a decision isn’t a correction. To be heard on one, see what’s coming up.

How a wetlands permit is decided

Work in tidal wetlands and along the shoreline, such as riprap, bulkheads and sills, needs a permit. The county's Wetlands Board decides these applications after an advertised public hearing.

Applications are also filed with the Virginia Marine Resources Commission, which assigns the application number used to follow a request.

The law: Va. Code § 28.2-1302 (Adoption of wetlands zoning ordinance; terms of ordinance). This describes the general process, not this decision.